After all loading, shipping and unloading works done, which take one month from this March, the 41T-32M STS crane built for the Beilun Second Terminal Subsidiary Company of Ningbo Port and 3 sets of 40T RTG cranes built for Ningbo Beilun International Container Terminals Limited Company are under commissioning and testing in owners' yards by Wison , and can be delivered in the coming April.
41T-32M STS Crane
The four cranes mentioned above are all completed by Wison, which contains design, procurement, construction, machine loading, lashing, shipping, unloading, and all the other work, and this remarks the succeed of the "turn key project" of such kind of cranes for first, and this also means the shipping for whole complete cranes successfully after the first practice of 4 sets of RMG cranes for Ningbo Zhenhai Port.
40T RTG Cranes
Wison finished loading and lashing on 2nd February 2010, shipping on 22nd, and starting unloading work on 3rd, March. All the workers worked hard until finished all the unloading work including the anchoring in the specified location, even to the early morning.
The succeed shipment of these two projects, both proofs the capacity of designing , but also fully demonstrates the unity and cooperation of the working team.